Tidewater Home Improvement LLC
Scope of Work & Estimate
5304 Doon Street · Virginia Beach, VA
5304 Doon Street crawlspace
$5,434 Estimate
5304 Doon Street · Virginia Beach, VA
Crawlspace Cleanup & Encapsulation Prep · 974 SF
Print / PDF Expires: 08/30/2026
Project Overview
Customer: Danny Carlisle
Project: Crawlspace Cleanup & Encapsulation Prep
Address: 5304 Doon Street, Virginia Beach, VA
Crawlspace: 974 SF
Access Door: Existing opening — replaced
Humidity Control: Dehumidifier + pump + discharge
Included Scope
10101Clean Out & Debris Removal$1,497.00
  • Remove debris and existing/old vapor barrier from the crawlspace floor
  • Complete haul-off and offsite disposal of all debris
VBVapor Barrier 6-mil White — 974 SFIncluded
  • Install new 6-mil white vapor barrier over the entire crawlspace floor
  • Included at no charge with the cleanout special
DRCrawlspace Door (PVC)$330.00
  • Replace existing crawlspace access door with new PVC door
DHDehumidifier — AprilAire E070 + Pump$2,750.00
  • Install new AprilAire E070 crawlspace dehumidifier
  • Condensation pump with discharge line run out of the crawlspace
10121Electrical — New Breaker + GFCI Outlet$497.00
  • New dedicated breaker run for the dehumidifier
  • GFCI-protected electrical connection
VTSeal Vents$360.00
  • Seal crawlspace vents for humidity control
Site Photos
Payment Schedule — 50 / 50
Draw 1 — Deposit
50%
$2,717.00 upon signing
Draw 2 — Final
50%
$2,717.00 upon completion
Itemized Estimate — one all-in price per line
10101 — Clean Out & Debris Removal$1,497.00
Vapor Barrier 6-mil White (974 SF)Included
Crawlspace Door (PVC)$330.00
Dehumidifier AprilAire E070 + Condensation Pump + Discharge Line$2,750.00
10121 — Electrical (New Breaker + GFCI)$497.00
Seal Vents$360.00
ESTIMATED PROJECT TOTAL$5,434.00
Terms & Conditions

By agreeing to these Terms and Conditions, the customer acknowledges and accepts the outlined responsibilities and scope of work.

Scope: All work described in the Included Scope above. Any work not listed is not included unless agreed in writing.

Structural excluded: piers, joist/beam repairs, subfloor sheet replacement, engineering, foundation modifications.

Owner supplies: none required.

Contractor supplies: 6-mil vapor barrier, PVC crawlspace door, AprilAire E070 dehumidifier, condensation pump and discharge line, electrical materials, vent-sealing materials.

MEP contingency: if live wiring/plumbing is found during the work, a change order covers rerouting.

Notes:
**Jobsite will be left clean once completed.
**Contractor is not responsible for damage caused inside the home while repairing the foundation.

Warranty:
**12 months workmanship.

Payment Terms:
· Total Project Cost: $5,434.00
· Deposit to Schedule: $2,717.00
· Final Payment: $2,717.00

Check is a preferred method.
**You can pay by credit card using the link below.
https://request.plastiq.com/pay-tidewater-home-improvement-llc
Cards not eligible for payment:
- Virtual Affirm credit card

Validity: one (1) week from the date above.